Point Bolivar - Houston Ship Channel - Demolition Operation --- --- Demolition activities will be conducted near the Bolivar Ferry Landing on a nearby derelict steel dry dock. Work will take place during daylight hours only from 7:00 a.m. to 6:00 p.m., daily. On-scene equipment and crews will include two material barges and the Spud Barge EMERGE IV. Periodic dive operations will take place near the demolition site. Mariners are urged to transit the area at their slowest safe speed to minimize wake. VHF-FM Channels: 11 and 16, POC: (727) 361-4019
Valid 2026-07-10 to 2026-12-20.
Position 29-21.92N 094-47.00W
USCG Heartland (Gulf) District Local Notice to Mariners 43/2026