US Coast Guard LNM - Northeast District (D1)
US · Last modified 11 Nov 2026, 18:53
Full content
Recent active messages
SECTOR NEW YORK, SUBMERGED LANDS ACT (SLA) General / LAA / RNA / Safety Zone A 500-meter Safety Zone will be enforced around Empire Wind operations from 8:00am, November 11, 2026, to 8:00am, November 18, 2026, Mariners are to avoid transiting within 500 meters of the following positions: C09: 40°20′25.307N, 073°26′50.160W; E08: 40°18′57.671N, 73°27′43.888W; D10: 40°19′34.629N, 73°25′59.594W; B05: 40°21′45.973N, 73°30′15.333W; D17: 40°18′24.335N, 73°19′59.229W; D19: 40°18′04.195N, 73°18′16.307W;
MAIN CHANNEL - HUDSON RIVER General / Marine Construction (Excluding Bridges) / Dredging Location: 41-37.37N 073-56.94W Tilcon New York, Inc. will conduct maintenance dredging at the Tilcon Clinton Point Quarry, Sheafe Road, Poughkeepsie, NY 12601, in the Hudson River near latitude 41°37'27.0" N, longitude 73°56'34.1" W. Work is anticipated to occur from November 16 through November 23, 2026, 24 hours a day, seven days a week. Operations will involve a barge-mounted crane equipped with an enviro
SECTOR SOUTHEASTERN NEW ENGLAND, EXCLUSIVE ECONOMIC ZONE (EEZ) - SECTOR SOUTHEASTERN NEW ENGLAND, TERRITORIAL SEA General / LAA / RNA / Safety Zone A 500-meter Safety Zone may be enforced around Ørsted Northeast Program operations from 8:00am, November 11, 2026, to 8:00am, November 18, 2026, Mariners are to avoid transiting within 500-meters of the following positions: Revolution Wind Lease Area 486 Offshore Substations (OSS): AF08: 41-12.60N 071-07.70W, AL11: 41-07.69N 071-03.54W. Sunrise Wind
BRONX RIVER General / Bridges Location: 40-49.69N 073-56.03W Bridge Name: Macombs Dam Bridge The Coast Guard proposes to temporarily modify the operating regulation that governs the Macombs Dam Bridge across the Harlem River, mile 3.2, between the Boroughs of Manhattan and the Bronx, New York City, New York. The bridge owner, New York City Department of Transportation (NYCDOT), submitted a request on August 31, 2026, to allow the bridge to remain in the closed position from February 1, 2027, thr
PRESIDENT ROADS - CHELSEA RIVER General / Bridges / Inspection NDT Corporation has another temporary bridge inspection and testing project planned for this year working for Hardesty and Hanover and for the MassDOT. Below are a few summary bullets for the Andrew McArdle bridge project (Meriden Street over the Chelsea River). • The owners of this bridge are the City of Chelsea and City of Boston. • No work will be conducted in the main channel at this crossing. • Work will be completed on the 12 i
WINTHROP HARBOR APPROACH - WINTHROP CHANNEL General / Marine Events / Regatta (Race) MA – WINTHROP – WINTHROP HARBOR – WINTHROP FROSTBITE SUNDAY SAILING SERIES – REGATTA – The Cottage Park Yacht Club is hosting the Winthrop Frostbite Sailing Series every Sunday, from 1:00 PM to 3:00 PM from November 8, 2026, to April 1, 2027, in and around the vicinity of Winthrop Harbor. The event will consist of approximately 15 sailing vessels 12’- 14’ in length with 2 support craft. The person responsible fo
MAIN CHANNEL - BAY RIDGE CHANNEL General / Marine Construction (Excluding Bridges) / Dredging Cashman Dredging and Marine Contracting Co., LLC will conduct environmental-remediation dredging operations in the Gowanus Canal, Brooklyn, NY, from the 3rd Street Bridge to the Hamilton Avenue Bridge, between approximately 40°40'33.80" N, 073°59'25.04" W and 40°40'05.39" N, 074°00'02.94" W. Operations are scheduled from November 16, 2026, through November 15, 2027, weekdays from 7:00 a.m. to 6:00 p.m.
NEWARK BAY - PORT NEWARK PIERHEAD CHANNEL General / Marine Construction (Excluding Bridges) / Boring and Core Samples Aqua Survey, Inc. will conduct sediment sampling in the Newark Bay Federal Navigation Channel, Newark, NJ, from November 9 through November 25, 2026. Operations will occur Monday through Friday, from 8 a.m. to 4 p.m. Vessels R/V TESLA and R/V PRATTIS will be on scene and monitoring VHF-FM Channels 13 and 16. The vessels can move on demand to avoid impeding navigation. Mariners ar
MAIN CHANNEL - EAST RIVER MAIN CHANNEL General / Bridges / Inspection On November 14, 2026, and November 17, 2026, between 6:00 a.m. and 2:00 p.m., a bridge traveler will be operated under the Brooklyn Bridge over East River at mile 0.8 to perform a bridge inspection. Mariners requiring full vertical clearance can contact the contractor via marine radio VHF-FM Ch. 13/16 or call 917-295-1856 or 917-471-2257. The traveler platform will be moved out of the navigable channel after work hours or when
MAIN CHANNEL - EAST RIVER MAIN CHANNEL General / Bridges / Inspection Location: 40-45.42N 073-57.28W Bridge Name: Queensboro Bridge Valid 2026-11-12 to 2026-11-14. USCG Northeast District Local Notice to Mariners 45/2026
MAIN CHANNEL - EAST RIVER MAIN CHANNEL General / Bridges / Maintenance Location: 40-45.42N 073-57.28W Bridge Name: Queensboro Bridge On November 13, 2026, between 9:00 a.m. and 2:00 p.m., a bridge traveler will be operated under the Queensboro Bridge over East River at mile 5.5 to perform bridge inspection. Mariners requiring full vertical clearance can contact the contractor via marine radio VHF-FM Ch. 13/16 or call 917-295-1856 or 917-471-2257. The traveler platform will be moved out of the na
PROVIDENCE RIVER APPROACH - PROVIDENCE RIVER General / Bridges / Inspection Location: 41-49.08N 071-24.22W Bridge Name: Point St Bridge From November 16, 2026, to November 20, 2026, between 8:00 am to 4:00 pm, a 28’ aqualift CAT (CT0790BL) will be utilized to inspect Point Street Bridge across Providence River at mile 7.5, in Providence, RI. Mariners requiring full horizontal clearance can contact the contractor via marine radio VHF-FM Ch 13/16 or by calling (410) 294-6092 or (207) 356-0242. Mar
BUZZARDS BAY MAIN CHANNEL - HOG ISLAND CHANNEL General / Marine Construction (Excluding Bridges) / Facilities, Barriers, Manmade Reefs, Riprap, Jetties / Dikes Location: 41-44.26N 070-37.51W 41-44.25N 070-37.47W 41-44.24N 070-37.50W 41-44.25N 070-37.53W 41-44.26N 070-37.51W ACK Marine will be conducting dive operations for fender repairs on the Mass Maritime Academy Pier. Request reduced speed when operating in the area. Valid 2026-11-13 to 2026-11-17. USCG Northeast District Local Notice to Mar
SECTOR SOUTHEASTERN NEW ENGLAND, SUBMERGED LANDS ACT (SLA) - BUZZARDS BAY MAIN CHANNEL General / Autonomous Vessel Operations The Woods Hole Oceanographic Institution (WHOI) will deploy the Pyxis AUV in Buzzards Bay (41.574, -70.721) after which it will transit the length of the Bay, turn (41.447, -71.008) and transit due south before returning along the same route 2-4 days later. The Intended track appears below. The autonomous underwater vehicle (AUV) is 9’ long and 12” in diameter. It is yell
HUDSON RIVER General / Bridges Location: 42-30.50N 073-46.46W Bridge Name: Alfred Smith Memorial Bridge CSX Railroad Bridge The navigational lights are not active on the CSX Alfred H. Smith Memorial Bridge, AKN Castleton Bridge, across the Hudson River, mile 135.8, between Selkirk and Castleton-on-the-Hudson, New York. CSX is obtaining parts. Estimated repair time is unknown at this time. Mariners are advised to proceed with caution and reduce wake. Valid 2026-11-10 to 2026-11-13. USCG Northeast
NEW ROCHELLE HARBOR NORTH APPROACH General / Bridges Location: 40-53.34N 073-46.95W Bridge Name: Glen Island Bridge The Coast Guard has issued a temporary deviation for the Glen Island Temporary Bridge. Under this temporary deviation, the Glen Island Temporary Bridge will not open for marine traffic from November 16, 2026 through November 18, 2026. Mariners that can pass without a bridge opening may do so and are advised to exercise caution when transiting the area. Valid 2026-11-10 to 2026-11-1
MAIN CHANNEL - BUTTERMILK CHANNEL General / Marine Construction (Excluding Bridges) / Facilities, Barriers, Manmade Reefs, Riprap, Jetties / Dikes Location: 40-40.98N 074-01.38W Mariners are advised that marine demolition and construction operations will be conducted at Yankee Pier, Governors Island, near Craig Road South and Half Moon Road, in the vicinity of 40°40'58.8"N, 074°01'22.8"W, from November 10, 2026, through December 6, 2028. Work includes demolition of existing piers and a boat hois
EAST RIVER MAIN CHANNEL General / Bridges Location: 40-47.96N 073-47.62W Bridge Name: Throgs Neck Bridge Beginning November 20, 2026 through July 16, 2026, contractor Navillus, will be performing pier rehabilitation at the Throgs Neck Bridge across East River at mile point 15.8. To perform this work contractors will be utilizing a barge, HUGHES 115 (114 ft x 35 ft x 8 ft, light draft 2 ft 6 in). Bridge rehabilitation will take place at pier 42, 44, and 17. Mariners with any questions can contact
BOSTON NORTH CHANNEL - PRESIDENT ROADS General / Marine Construction (Excluding Bridges) / Boring and Core Samples Location: 42-20.77N 071-01.38W 42-20.73N 071-01.38W 42-20.72N 071-01.51W 42-20.74N 071-01.51W 42-20.77N 071-01.38W MASSACHUSETTS – BOSTON – BOSTON INNER HARBOR – NORTH JETTY- Jetty Boring Operations Mariners are advised that Childs Engineering and Ocean Surveys Inc will be conducting core sampling in the vicinity of the North Jetty from November 3, 2026, through November 13, 2026. W
SLOOP CHANNEL General / Bridges Location: 40-35.95N 073-32.59W Bridge Name: Meadowbrook State Parkway Bridge Due to a mechanical failure, the south leaves of the Meadowbrook State Parkway Bridge across Sloop Channel at mile 12.8 are inoperable until further notice. The bridge can still open in accordance with its operating schedule but can only open the north leaves of the bridge, providing open vertical clearance of 37.5’ at the North side of the channel. Updates regarding the status of repairs
RARITAN RIVER CUTOFF CHANNEL - RARITAN RIVER General / Bridges / Construction Construction and demolition operations to replace the Raritan River Railroad Bridge commenced on April 1, 2026, and will continue through January 18, 2030. A channel closure is tentatively scheduled for the week of November 30, 2026. The actual closure date will be weather dependent and communicated with local mariners as the operation gets closer. Operations through December 2026 include counterweight Installation at
WEST PASSAGE - POINT JUDITH HARBOR OF REFUGE General / Hazards To Navigation / Obstructions Blue Acres Aquaculture will conduct seaweed aquaculture operations in the Harbor of Refuge, Point Judith, Narragansett, Rhode Island, from November 1, 2026, through May 1, 2027. The aquaculture site is bounded by the following approximate positions: 41°21'33.95" N, 071°30'29.95" W; 41°21'24.95" N, 071°30'34.67" W; 41°21'32.23" N, 071°30'25.88" W; and 41°21'23.14" N, 071°30'30.46" W. Mariners are advised o
RARITAN RIVER CUTOFF CHANNEL - ARTHUR KILL General / Marine Construction (Excluding Bridges) / Dredging Bird Construction will conduct dredging operations in Smith Creek Inlet from November 14, 2026, through January 15, 2027, between 7 a.m. and 5 p.m., daily. Multiple deck scow barges, a dredge barge, towing tug, a 60-foot by 125-foot crane barge, and a 37-foot by 150-foot hopper barge will be operating in and near the navigable channel in the vicinity of 40°32'43.7" N, 074°15'12.7" W. No vessel
HOG ISLAND CHANNEL - CAPE COD CANAL EASTERN ENTRANCE General / Threatened And Endangered Species Advisory (TESS Advisory) / Marine Wildlife Migration NOAA FISHERIES ANNOUNCES THAT A VOLUNTARY VESSEL SPEED RESTRICTION ZONE UNDER THE RIGHT WHALE SLOW ZONE PROGRAM IS CURRENTLY IN EFFECT IN CAPE COD BAY, MASSACHUSETTS TO PROTECT RIGHT WHALES. THIS RIGHT WHALE SLOW ZONE IS IN EFFECT THROUGH NOVEMBER 17, 2026. NOAA REQUESTS MARINERS TO ROUTE AROUND THIS ZONE OR TRANSIT THROUGH IT AT TEN KNOTS OR LESS.
BOSTON NORTH CHANNEL - PRESIDENT ROADS General / Bridges / Repairs, Painting, Or Fender Replacement Location: 42-22.80N 071-03.11W Bridge Name: Chelsea St Bridge MA - BOSTON INNER HARBOR – LITTLE MYSTIC – CHELSEA STREET BRIDGE- Bridge Painting and Repairs Mariners are advised that SPS New England will be conducting Bridge painting and maintenance to the Chelsea Street Bridge mile 0.2 across thew Little Mystic channel. Work will commence on Monday September 14, 2026, and continue through Saturday
Same country
- US - HYDROARC31 active
- US - HYDROLANT78 active
- US - HYDROPAC157 active
- US Coast Guard LNM - Arctic District (D17)61 active
- US Coast Guard LNM - East District (D5)372 active
- US Coast Guard LNM - Great Lakes District (D9)110 active
- US Coast Guard LNM - Heartland District Gulf (D8)296 active
- US Coast Guard LNM - Heartland District Rivers (D8)70 active
- US Coast Guard LNM - Northwest District (D13)111 active
- US Coast Guard LNM - Oceania District (D14)18 active
- US Coast Guard LNM - Southeast District (D7)289 active
- US Coast Guard LNM - Southwest District (D11)99 active