GALVESTON BAY ENTRANCE CHANNEL - HOUSTON SHIP CHANNEL
General / Marine Construction (Excluding Bridges) / Facilities, Barriers, Manmade Reefs, Riprap, Jetties / Dikes
Houston Ship Channel - Dock Construction --- To: January 2027 --- Construction for a new barge dock will take place along the Houston Ship Channel near Houston Ship Channel Lighted Buoy 145 (LLNR-25785.01). Operations will be conducted 10-hours a day, 5-days a week. On-scene vessels will include two 150 ft x 60 ft crane barges, two material barges, four towing vessels, and a work raft. Mariners are urged to transit the area with caution. VHF-FM Channel: 16
Valid 2026-06-03 until further notice.
Position 29-44.07N 095-08.47W
USCG Heartland (Gulf) District Local Notice to Mariners 43/2026