NEW ORLEANS HARBOR - NEW ORLEANS TO BATON ROUGE
General / Marine Construction (Excluding Bridges) / Facilities, Barriers, Manmade Reefs, Riprap, Jetties / Dikes
Mississippi River - Pump Station Construction --- --- Pump station construction will be conducted along the Mississippi River, Mile 175.5, RDB, AHOP, Smoke Bend Crossing. Work will be conducted from 6:30 a.m. to 5:00 p.m., 6-days a week. Operations will include pile driving, excavation, and pipe installation. On-scene vessels will include a crane barge, a material barge, a towing vessel, and a crew boat. Mariners are requested to transit the area at a slow bell so as not to interfere with ongoing construction and proceed with caution. VHF-FM Channel: 67
Valid 2025-11-28 to 2026-12-13.
Position 30-06.55N 090-59.38W
USCG Heartland (Gulf) District Local Notice to Mariners 40/2026