ELK RIVER CHANNEL - SUMMIT BRIDGE TO BULL MINNOW POINT
General / Bridges / Inspection
Location: 39-32.48N 075-44.30W Bridge Name: 896 State Route Bridge Mariners are advised that contractors will be performing bridge maintenance and painting operations of the Summit Bridge, at mile 9.7, over the C&D Canal in Middletown, D.E. The maintenance and painting operations will be performed from 7 a.m. to 5 p.m. starting on June 23, 2025, and ending December 15, 2026. To facilitate the work, a decking platform will reduce the available vertical clearance to approximately 128 feet above mean high water. Mariners should use caution when transiting the area. MSI #53481.
Valid 2026-09-10 to 2027-03-09.
USCG East District Local Notice to Mariners 47/2026