MAIN CHANNEL - EAST RIVER MAIN CHANNEL
General / Marine Construction (Excluding Bridges) / Facilities, Barriers, Manmade Reefs, Riprap, Jetties / Dikes
Location: 40-48.25N 073-55.83W Trevcon Construction Company will be conducting demolition and reconstruction operations on the Harlem River, west shoreline from RFK Bridge(125th St.) to Metro North Rail Bridge (132nd St.)in position 40-48.25N 073-55.83W, through August 2027, Monday through Friday, between 5:00am to 6:00pm. Equipment on scene will be multiple crane barges, and material barges, monitoring VHF-FM CH 13, 16, 65, &75. Floating Equipment will be positioned along the West shoreline of the Harlem River, vessel traffic will not be impeded.
Valid 2026-03-20 to 2027-08-31.
USCG Northeast District Local Notice to Mariners 47/2026