HomeMapSky mapAlpha
More
Account
Loading…
Language: English

MPB-85229572

SÉCURITÉ

Hydrological survey off Tongxiao Power Plant, Taiwan; ocean current meter deployment 17 Sep-17 Oct 2026

No longer in forceReceived 16 Sept 2026, 00:00 UTCArchived 18 Oct 2026, 13:10 UTC

Warning text

HYDROLOGICAL SURVEY WORKS FOR THE "2024–2026 MARINE ENVIRONMENTAL INVESTIGATION AND SPECIFIC SEA AREA WASTEWATER DISCHARGE PERMIT APPLICATION" OF TAIWAN POWER COMPANY TONGXIAO POWER PLANT Source:Ji Qing Environmental Engineering Office, letter No.1150134 dated September 15,2026. 1.Considering the recent sea state conditions and actual offshore operation scheduling, the hydrological survey operations originally planned to commence on September 29, 2026.have been adjusted. The deployment of the Ocean current meter will now begin on September 17, 2026, and will be carried out continuously for 31 days. Please note that the actual operation dates remain subject to adjustment based on the sea state conditions of the day. 2.To facilitate flexible scheduling for offshore operations, the project contractor proposes to add "Wayten Technology Co., Ltd." to work alongside " Dawu Ocean Research Ecology CO., LTD." as joint executing entities. Actual operations will be scheduled and dispatched based on the manpower, vessels, and operational requirements of the day. 3.Please refer to the attachment for detailed information. Vessels transiting these waters are advised to navigate with caution. MPB notice 333-SRY8105-20260916005

Analysis

No longer in force

Hydrological survey operations for Taiwan Power Company Tongxiao Power Plant will deploy an ocean current meter offshore. Deployment began 17 September 2026 and is planned to continue for 31 days, with actual dates subject to change due to sea state. Wayten Technology Co., Ltd. has been added as a joint contractor alongside Dawu Ocean Research Ecology Co., Ltd. Vessels transiting the area are advised to navigate with caution.

Type
Survey operations · severity moderate
Feed
Survey operationsAll warnings of this kind on the map, or as an API feed.
Location
Offshore Tongxiao Power Plant, Taiwan
Validity
From 17 Sept 2026, 00:00 UTC
Until 17 Oct 2026, 23:59 UTCThe deployment of the Ocean current meter will now begin on September 17, 2026, and will be carried out continuously for 31 days.
Activity periods
  • 17 Sept 2026, 00:00 UTC - 17 Oct 2026, 23:59 UTC (continuous for 31 days from 17 Sep 2026; actual dates subject to adjustment based on sea state)
Hazards
hydrological survey, ocean current meter deployment, survey vessels/operations

Worked out automatically from the warning text on 30 Sept 2026, 10:12 UTC. It can be wrong: the official warning text is the authority.

The whole analysis comes with Lagom

This warning's analysis also has:

  • Action for mariners
  • Translations

The action for mariners, the keep-clear distance, contacts, ships named, translations and the nearby lights and rescue centres come with Lagom and every higher plan, and with the API plans. The official warning text above is always free.

Keywordssurvey operationsoffshore operations

Beta look