DECEPTIONPASS - SKAGIT BAY
General / Bridges / Repairs, Painting, Or Fender Replacement
Washington State Department of Transportation (WSDOT) will be cleaning and painting the Division Street Bridge (LLNR 18783) across the Skagit River, mile 12.5, in Mount Vernon, WA. Construction will occur 24-hours a day and seven days per week from 0600 on 01 May 2026 to 2359 on 31 December 2026. Containment system will be attached to half of the bridge 24-hours a day and will prevent falling debris. Containment will reduce the vertical clearance on half of the bridge from 18.5 feet to 6.75 feet above high water, The containment will be marked with amber caution lighting. Work will not occur in the water, although one support vessel will be needed for worker safety. Mariners are advised to use caution while transiting the area. For additional information, contact Mr. Shane Spahr, P.E. at (360) 757-5990 or [email protected]
Position 48-25.28N 122-20.38W
USCG Northwest District Local Notice to Mariners 45/2026