Dredging operations will be conducted at the Phillips 66 Marine Terminal in Rodeo, California, using clamshell dredge DB BEAVER, DB24, or DB POINT LOMA. Operations will occur on or about November 15 through November 30, 2026, 24 hours a day, seven days a week. The project area is located at approximately: 38-03.37N 122-15.83W. Dredged material will be loaded into five split-hull scows, with capacities of 2,000 and 3,000 cubic yards, and transported to the Montezuma Wetlands Restoration Project disposal site by tow tug HEIDI L BRUSCO, ARTHUR BRUSCO, or a similar vessel. Tender tug BECKY T or PHYLLIS T will provide support. All project equipment will monitor VHF-FM Channels 13, 14, and 82. For further information or comments, contact Superintendent Dennis Salyers at 415-497-5289 or the project representative at 415-218-6739. All mariners are advised to transit the area with caution.
USCG Southwest District Local Notice to Mariners 47/2026