Porto-Vecchio harbour enlargement and dredging works, Maddalena

ActiveReceived 20 May 2026, 11:40 UTC

Warning text

Lang
Area: MADDALENA Locality: PORT DE PORTO-VECCHIO BREAKWATER_CONSTRUCTION WHARF_CONSTRUCTION WORKS_IN_PROGRESS DREDGING_OPERATION EVERY DAY FROM 06H00 UTC TO 17H00 UTC ENLARGEMENT OF THE PORT OF PORTO-VECCHIO IN THE AREA DELIMITED BY: 41-35.62N 009-17.07E/41-35.61N 009-17.20E 41-35.70N 009-17.39E/41-35.56N 009-17.50E 41-35.56N 009-17.58E/41-35.65N 009-17.92E 41-35.59N 009-17.84E/41-35.55N 009-17.69E 41-35.39N 009-17.53E/41-35.38N 009-17.50E 41-35.37N 009-17.47E/41-35.30N 009-17.35E 41-35.35N 009-17.27E/41-35.33N 009-17.24E 41-35.34N 009-17.05E/41-35.42N 009-16.96E 41-35.59N 009-17.04E INSTALLATION OF PONTOONS, CONSTRUCTION OF MOLE WHARF, PILE 13, INSTALLATION OF MOORING LINES, INSTALLATION OF ARTICULATED PILES, EARTHWORKS NORTH BREAKWATER, RESUMPTION OF DREDGING/ROCK-REMOVAL OPERATIONS WITH THE ASSISTANCE OF THE FOLLOWING NAVAL UNITS: PONTON JACK UP BAARS (GRUE EMBARQUEE 90T) PONTON BAARS DE SERVITUDE NAVIRES MULTICAT DEAUVILLE, OCTOPUS, ROUDADOU WEST PART - NORTH AND SOUTH PARTS CIVIL ENGINEERING SOUTH-WEST PART CONSTRUCTION OF QUAYS WORKS_IN_PROGRESS INSTALLATION OF 4 PILES IN THE NAVIGABLE AREA (OUTSIDE THE CHANNEL) UNTIL THE DEFINITIVE BUOYS ARE INSTALLED. THE PERIMETER OF THE WORKS AREA AROUND THE PILES EXTENDS TO A RADIUS OF 30 METRES AROUND THE POSITIONS: A 41-35.52N 009-17.48E B 41-35.52N 009-17.47E C 41-35.53N 009-17.47E D 41-35.54N 009-17.46E NAVIGATE WITH CAUTION AND GIVE A WIDE BERTH

Analysis

Active

Construction and dredging works are in progress in the Port de Porto-Vecchio, Maddalena. Activities include breakwater and wharf construction, installation of pontoons and piles, mooring lines, earthworks and rock-removal dredging. Works take place every day from 06:00 to 17:00 UTC and four piles in the navigable area have 30 metre safety radii around them until permanent buoys are installed. Mariners are advised to navigate with caution and give a wide berth.

Type
Offshore operations · severity moderate
Feed
Offshore works, rigs and towingAll warnings of this kind on the map, or as an API feed.
Location
Maddalena, Port de Porto-Vecchio
Activity periods
  • ? - ? (every day 06:00-17:00 UTC)
Hazards
dredging, rock-removal, breakwater construction, wharf construction, installation of piles, floating and jack-up pontoons, work vessels and multicats, temporary safety radii around piles

Worked out automatically from the warning text on 28 Oct 2026, 23:29 UTC. It can be wrong: the official warning text is the authority.

The whole analysis comes with Lagom

This warning's analysis also has:

  • Action for mariners
  • Keep-clear distance
  • Ships named
  • Translations
  • Nearby lights and rescue centres

The action for mariners, the keep-clear distance, contacts, ships named, translations and the nearby lights and rescue centres come with Lagom and every higher plan, and with the API plans. The official warning text above is always free.

Beta look